La Romaine 4 – Excavation and concreting of the temporary diversion
As part of the construction of the 1550 MW hydroelectric complex on the Romaine River, Hydro-Quebec granted EBC the contract for the excavation and concreting of the temporary diversion of La Romaine 4.
- Overburden excavation of both headrace and tailrace.
- Rock excavation of both headrace and tailrace by drill and blast.
- Excavation of the temporary diversion tunnel.
- Concreting of the portal.
- Construction of a 34.5 kV electrical distribution line.
- Construction and maintenance of roads and temporary boarding area.
Features
- Activity Sector Energy
- Client Hydro-Québec
- Year 2017-2018
- Value $27,000,000
Place