Project
Share the project

La Romaine 4 – Excavation and concreting of the temporary diversion

As part of the construction of the 1550 MW hydroelectric complex on the Romaine River, Hydro-Quebec granted EBC the contract for the excavation and concreting of the temporary diversion of La Romaine 4.

  • Overburden excavation of both headrace and tailrace.
  • Rock excavation of both headrace and tailrace by drill and blast.
  • Excavation of the temporary diversion tunnel.
  • Concreting of the portal.
  • Construction of a 34.5 kV electrical distribution line.
  • Construction and maintenance of roads and temporary boarding area.

Features

  • Activity Sector Energy
  • Client Hydro-Québec
  • Year 2017-2018
  • Value $27,000,000
Place